Vital GRP project case study
College Park ASHP Enclosure GRP Access Steps and Grating
A prefabricated GRP access package developed for the air-source heat-pump enclosure at College Park.

Planning a rooftop access package? Bring the plant layout, steelwork and access requirements together.
Discuss your access packageProject sheet: explore the illustrated project story.
Download PDF case study01 · Challenge
Coordinate access around rooftop plant.
The project concerns GRP access steps and a grating floor for rooftop plant at College Park School, Garway Road, Westminster. The package connects the access level with a working surface supported by the existing steel arrangement.
The Revision B proposal distinguishes 38 mm grating treads for the access steps from approximately 66.2 m² of 50 mm open-mesh enclosure flooring. The construction drawing develops the step geometry, panel layout and fixing details. Proposal quantities describe the quoted basis, rather than an as-built measurement.
02 · Specification
Match treads, floor panels and fixing interfaces.
Prefabricated step
The step arrangement combines GRP channel framework, mid-stringer support, 38 mm grating treads and ergonomic handrail. The construction drawing develops the overall geometry and connection to the supporting structure.
Modular floor
The 50 mm open-mesh floor is set out around existing steel beams, columns and baseplates. The construction drawing identifies panels for full-width supply and site trimming around the existing interfaces.
Controlled fixing
The drawing records J-clamp and M-clip details at steel supports, with a G-clamp detail at panel joints. Fixing selection follows the actual support and joint condition.

03 · Delivery
A supply scope fitted to supporting steelwork.
The pre-start plan requires weekend delivery and coordination of the roof lifting and landing arrangements with the client. It also identifies roof loading, edge protection, access and step-foot interfaces as items to resolve before installation. The construction drawing coordinates panel cuts around steel columns and baseplates.
Project photographs show the Vital GRP team fitting the floor around the steelwork and services, with the access steps and contrasting yellow leading edges in position.

04 · Outcome
A defined arrangement for the plant enclosure.
The documented package combines a GRP access step, a 50 mm open-mesh floor and connection details around the existing steel support layout. The installation photographs show open-mesh flooring arranged around the steel columns and a defined stepped approach with handrails and contrasting yellow tread edges.
Standards and assurance: Project-specific layout and fixing coordination. Final support and installation requirements follow the accepted project information.
Evidence note: Project P1685; QU1079 Revision B; pre-start plan; construction drawing revision C01. These describe the proposal and coordinated scope; a completion date and as-built quantities are not stated here.
Record the step, service face and roof support together
For similar rooftop heat pump projects, show the approach level, the working side of the plant and the steelwork or other structure that receives the deck. This illustrative detail helps coordinate the access package with the equipment and roof drawings.

Read the drawing notes
- Start at the access level. Record the approach and the change in level onto the working deck.
- Mark the service face. Confirm which side needs routine access and room for maintenance.
- Survey the support. Show the deck edges and supporting steelwork, plus any gaps and clashes.
Planning a similar project?
Does your rooftop plant need coordinated access?
Existing steelwork and equipment positions determine the support, tread and floor-panel arrangement.
Send the plant and steelwork drawings, levels and required maintenance routes. We can help review the supply scope and interfaces.
Discuss rooftop plant access